LIBN: LIRR’s Third Track is completed

LIRR’s Third Track is completed

By: Adina Genn October 3, 2022

 

The Long Island Rail Road’s 10-mile Third Track from Floral Park to Hicksville has been completed.

New York State Gov. Kathy Hochul was at the LIRR’s Westbury station Monday to say that the Third Track – part of the $2.5 billion LIRR Main Line Expansion Project – was completed nearly four years after breaking ground, on schedule and $100 million below budget.